Hi Jeremy, this is quite a usefull article. I have a question on managing EWN's. If my contractor gives me an EWN on a delay that is concurrent. For example, if I were to supply a door for a room but the contractor has not yet completed procurement on the Bricks yet. Would the EWN stand for the door? is there a way to call his bluff?